Busan Newport
  • Scale: Construction of 30 container terminal berths
    • Stage 1 (2008): 14 container terminal berths
    • Stage 2 (2011): 13 container terminal berths
    • Stage 3 (2015): 3 container terminal berths
  • Operational Expenditure: 10.644 trillion won (government: 5.1737 trillion won; civilian: 5.4703 trillion won)
Implementation Schedule
  • Stage 1 (2008) - Secure 14 berths
    • Multi Purpose Terminal (government): 1 berth => Commenced construction in February 2002; Completed construction in March 2007
    • North 'Con' Terminal (civilian investment): 13 berths => 3 berths in 2005; 3 berths in 2006, 7 berths in 2008.
  • Stage 2 (2011) - Secure 13 berths
    • South 'Con' Terminal (government): 4 berths => Commenced construction in December 2004; will complete construction in 2009
    • South 'Con' Terminal (civilian investment): 7 Terminals => Commenced in July 2007 on 4 berths as stages 2-3; commenced negotiation in April 2007 for 3 berths as stages 2-4
    • West 'Con' Terminal (civilian investment): 2 berths => Place an order for basic and implementation design in February 2008 (expected)
  • Stage 3 (2015) - Secure 3 berths
    • West 'Con' Terminal (civilian investment): 3 berths => Placed an order for basic design in December 2007