Multi Purpose Terminal (government): 1 berth => Commenced construction in February 2002; Completed construction in March 2007
North 'Con' Terminal (civilian investment): 13 berths => 3 berths in 2005; 3 berths in 2006, 7 berths in 2008.
Stage 2 (2011) - Secure 13 berths
South 'Con' Terminal (government): 4 berths => Commenced construction in December 2004; will complete construction in 2009
South 'Con' Terminal (civilian investment): 7 Terminals => Commenced in July 2007 on 4 berths as stages 2-3; commenced negotiation in April 2007 for 3 berths as stages 2-4
West 'Con' Terminal (civilian investment): 2 berths => Place an order for basic and implementation design in February 2008 (expected)
Stage 3 (2015) - Secure 3 berths
West 'Con' Terminal (civilian investment): 3 berths => Placed an order for basic design in December 2007